Four laning of NH-365A from Kodad (Design Km 0.00/Existing Km 185.00 of NH-65) to Khammam (Design Km 31.800/Existing Km 29.400) (Design Length = 31.800 Km) in the State of Telengana under Bharatmala Pariyojna on Hybrid Annuity Mode

Scope of Work

Construction of 4 lane Highway including construction of Major Bridges, Minor bridges, Vehicular Underpasses, Light Vehicular Underpasses, Culverts, Drains, Service Roads, etc. .

Client

National Highways Authority of India (NHAI)

Construction Period

2 years (730 days)

Length in KM

31.80 km

O&M Period

15 years

Concession Agreement Date

15.07.2021

Appointed Date

15.01.2022

Pavement Classification

Flexible Pavement for Main Carriageway and Service/Slip Road, Rigid Pavement for Toll Plaza